Queen Avenue repaving almost finished

Written October 19th, 2024 by Hasso Hering

New paving on Queen Avenue west of Marion Street was being finished on Saturday afternoon.

Traffic should soon be able to get back on Albany’s Queen Avenue from Pacific Boulevard as a contractor winds up a $4 million reconstruction and repaving project.

Since June, North Santiam Paving, of Stayton, has been working on Queen Avenue between Marion Street and Pacific Boulevard. The job included installing new water lines and rebuilding the eastern section of the street. The section between Ferry Street and Pacific was repaved.

On social media,  people were asking when the Queen Avenue closure at Pacific would end. Chris Cerklewski, the engineer in Albany Public Works overseeing the project, told me Friday:

“Weather permitting, the remainder of the paving will be completed on Saturday with striping work beginning on Tuesday next week. The plan is to get the striping from Pacific Boulevard to Ferry Street done first, so that section of Queen Avenue can be reopened to through traffic by the end of the day on Tuesday.  Queen Avenue from Ferry Street to Marion Street will reopen to through traffic later that week once the remaining striping has been completed.”

On Saturday, the weather did indeed permit. On a bike ride along the sidewalk on the south side of Queen, I could see that the last layer of asphalt  had been laid down.  A roller was at work giving the new pavement a final touch.

This City of Albany project did not include the Queen Avenue railroad crossing itself. Improvements there are part of an ODOT and railroad project that has been planned and delayed for years and may happen in 2025 — or after that. (hh)

Queen Avenue east of Pacific should be reopened in a matter of days. This was shot Saturday afternoon.





7 responses to “Queen Avenue repaving almost finished”

  1. DPK says:

    Good timing. Sounds like maybe a soaking or two soon.

  2. Elizabeth Harrison says:

    I cannot believe they couldn’t coordinate with ODOT and the railroad folks to FIX THE JACKED-UP RAILROAD CROSSING at the same time, so citizens aren’t burdened with another road closure. Idiots!!

  3. Elaine Gay says:

    Finally!!!!

  4. anonymouse17 says:

    So all of Queen Ave. will be open by the end of next week? So it is Queen Avenue from Pacific Blvd. S. to Ferry and then Queen Avenue from Ferry to Marion? And that’s it. That is all they have been working on all this time?

    • Kevin Thoma says:

      Yeah, it wasn’t just repaving the road. Reading is hard, so you must have missed where they replaced water lines and stuff.

Leave a Reply

Your email address will not be published. Required fields are marked *

 

 
HH Today: A perspective from Oregon’s mid-Willamette Valley
Albany Albany City Council Albany council Albany downtown Albany housing Albany parks Albany Planning Commission Albany police Albany Post Office Albany Public Works Albany riverfront Albany schools Albany Station Albany streets Albany traffic Albany urban renewal Amtrak apartments ARA Benton County bicycling bike lanes Bowman Park Bryant Park CARA climate change COVID-19 Cox Creek Crocker Lane cumberland church cycling Dave Clark Path downtown Albany Edgewater Village Ellsworth Street bridge Highway 20 homeless housing Interstate 5 land use Linn County Millersburg Monteith Riverpark North Albany North Albany Road ODOT Oregon legislature Pacific Boulevard Pacific Power Portland & Western Queen Avenue Railroads Republic Services Riverside Drive Santiam Canal Scott Lepman Talking Water Gardens The Banks Tom Cordier Union Pacific urban renewal Water Avenue Waterfront Project Waverly Lake Willamette River


Copyright 2024. All Rights Reserved. Hasso Hering.
Website Serviced by Santiam Communications
Hasso Hering