A move, maybe, in Talking Waters lawsuit

Written September 27th, 2026 by Hasso Hering

One of the signs at Talking Water Gardens still explains how it’s supposed to work.

Nine years after Albany sued the engineers who designed Talking Water Gardens, the lawsuit remains pending in Linn County Circuit. But now there may be a development.

Judge Michael Wynhausen had scheduled a hearing in the case, City of Albany v. CH2M-Hill, for July 27 but canceled the hearing when CH2M said the parties would try mediation.

The week before the scheduled hearing on motions, a lawyer for CH2M wrote the court:

“The City and CH2M have agreed to pursue mediation in this matter and request that the court vacate the July 27 hearing date on CH2M’s motion to strike subject to later rescheduling, as well as all other pending deadlines, while they engage in mediation processes.”

In response, the judge’s judicial assistant emailed: “I have canceled the July 27 hearing and will tickle the case for review on Nov. 17, 2026.”

After finding this correspondence in the case file at the courthouse, I asked City Attorney Sean Kidd if mediation had begun and whether an end of the litigation was in sight.

On Sept. 14 he replied: “No mediation has occurred yet and no end in sight as far as I can see.”

Talking Waters was completed in 2012. The system of ponds and waterfalls was intended to cool treated wastewater from the Albany-Millersburg sewage treatment plant before the water is pumped into the Willamette River.

The ponds leaked underground, and the system was shut down in December 2024 because the state Department of Environmental Quality considers the leakage to be an unauthorized discharge in violation of law.

CH2M designed the system, and the city sued the company for many millions of dollars in 2017. The company responded that it was not at fault. Among other things it said it was the city that decided against a recommendation to have the ponds lined.

Last summer and again since this Aug. 26, the city has pumped water into the Water Gardens from Cox Creek to keep the plants from dying.

Talking Waters, off the end of northeast Waverly Drive, remains open to the public. Some of the ponds have water in them now, and the paths are a nice place for a walk. (hh)

Water cascades down the main falls at Talking Water Gardens on Sept. 22, 2026.





5 responses to “A move, maybe, in Talking Waters lawsuit”

  1. AnonymousOldster says:

    So, “to cool treated wastewater from the Albany Sewage System,” was the original purpose (other than purpose to have paths and plants and ponds/streams and trails in a park-like area). Was any of that treated wastewater industrial discharge, or was it all ordinary domestic waste? If it is true that Albany decided against having the ponds lined, seems to me the case is pretty cut-and-dried not CH2M Hill’s fault. (Well, the company used to be called CH2m Hill, so my mind went back to that name.) But, since it is a deadlocked case, apparently the city of Albany had some points in their favor.

    • Dala Rouse says:

      As far as I know Ch2M Hill recommended to the city that liners were not needed when they actually were. The discharge was from the cities wasted water plant and Wah Chang. Wah Changs discharge is cooler than cities so they mixed the two to cool the discharge to the river. If I remember right Wah Chang paid for part of Talking Waters.

  2. Jill Van Buren, Coordinator AAP & GC says:

    You missed the “Big Plant” at North Albany Natural Area yesterday.

    Adopt a Park volunteers planted over 230 oaks, to create an Oak Savana out there. Just one of the 20+ events, so far this year, that Adopt A :Park have given to the City.
    Photos will be appearing on the Parks and Rec website soon.

  3. AnonymousOldster says:

    Ponds, pond liners….where have I heard discussion of that recently?

  4. gregory mills says:

    I havent heard if the state DEQ was involved with the approval process in the beginning? Did not anyone realize that when water is put on dirt it soaks in to the water table below? Who are the responsible leaders for Albany for this situation and if at fault are they being held accountable?
    Are they the same people who benefited from the faulty sewer treatment plant that had problems when installed and fled?

    Sounds alot like Mercury creek is flowing into Possum lake next to Port Asbestos

 

 
HH Today: A perspective from Oregon’s mid-Willamette Valley
"plaza street" Albany City Council Albany council Albany downtown Albany parks Albany police Albany riverfront Albany Station Albany streets Albany Waterfront Project apartments Benton County bicycling Bowman Park CARA Cox Creek Dave Clark Path demolition DEQ downtown downtown Albany Ellsworth Street bridge Ferry Street Highway 20 homeless homeless camps housing Landmarks Commission land use Linn County middle housing Millersburg Monteith Riverpark North Albany North Albany Road ODOT Pacific Boulevard Pacific Power parks pavement Periwinkle Bikepath Periwinkle Creek photo enforcement Portland & Western potholes Queen Avenue railroad Railroads red light cameras Salem Avenue Santiam Canal Santiam Road Simpson Park speed cameras Talking Water Gardens traffic traffic cameras Union Pacific urban renewal vandalism Water Avenue Waterfront Project Waverly Drive Waverly Lake Willamette River



Copyright 2025. All Rights Reserved. Hasso Hering.
Website Serviced by Santiam Communications
Hasso Hering